The problems with time outlined above were exacerbated by the inclusion of a `work package 0', without a corresponding extension to the overall timeline. Whilst a general analysis of Castep performance was necessary, the detailed option-by-option study requested by NAG was unexpected and it would have been better to set aside an extra month for this work rather than try to fit it into the existing timeframe.
One final frustration with the general schedule of the project was the holiday allowance. Due to various negotiations between NAG and the University of York regarding the precise financial arrangements, the holiday allowance was set at seven weeks, which was of course extremely generous. Unfortunately at nearly 20% of the project time it was completely impractical to actually use most of this allowance and still expect to get the work done.
Despite these misgivings, the project has been very successful. The
original goal of the project was to improve the scaling of Castep with
cores by `a factor of 8 or more to over 2000'. Despite the lack of the
fourth phase's parallel band-independent optimiser, the scaling of
Castep has been improved by about a factor of four, and with the extra
work on -point optimisations the target factor of eight or
more in performance awaits only the integration of the band-parallel
developments with the latest Castep source.
The considerable computational resources of HECToR, coupled with the developments in Castep detailed in this dCSE project report, should enable accurate DFT calculations on a far greater scale than has been possible to this point.